File #: 2024-1623   
Category: Consent Item Status: Agenda Ready
File created: 12/11/2024 Type: Board of County Commissioners
On agenda: 1/14/2025 Final action:
Title: Approve Change Order #1 to CC-5663-24/TAD - Construction of the Central Transfer Station Tipping Floor with Cornerstone Construction Services, Inc. in the amount of $121,754.38 and authorize the Purchasing & Contracts Division to execute the Change Order. District2 - Zembower (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Environmental Services
Attachments: 1. CC-5663-24 Change Order 1 (Cornerstone).pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

title

Approve Change Order #1 to CC-5663-24/TAD - Construction of the Central Transfer Station Tipping Floor with Cornerstone Construction Services, Inc. in the amount of $121,754.38 and authorize the Purchasing & Contracts Division to execute the Change Order. District2 - Zembower (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Environmental Services

end

Division:

division

Resource Management - Purchasing and Contracts

body

Authorized By:

Lorie Bailey Brown, CFO/Resource Management Director

Contact/Phone Number:

Tony Durrum/407-665-7123

Background:

CC-5663-24/TAD provides for the rehabilitation of the Central Transfer Station Tipping Floor through selective demolition of the exiting tipping floor, repair of the pit edge and the concrete floor filler installation with steel reinforcement.

Change Order #1 provides additional steelwork needed for the rehabilitation of the Tipping Floor.

The following is a summary of the cost of the Agreement:

Original Agreement Sum: $2,067,069.50

Change Order #1:             $121,754.38

Revised Agreement Total: $2,188,823.88

This is a budgeted project, and funds are available in Transfer Station Refurbishment (00244517.560650) (6509999901)

Requested Action:

Staff requests the Board approve Change Order #1 to CC-5663-24/TAD - Construction of the Central Transfer Station Tipping Floor with Cornerstone Construction Inc. in the amount of $121,754.38 and authorize the Purchasing & Contracts Division to execute the Change Order.