Title: Approve and authorize the Chairman to execute a Resolution authorizing the County Manager to execute the Loan application and apply for a Loan through the Clean Water State Revolving Fund program, to provide assurances required by the Loan application, and delegate responsibility to appropriate Seminole County staff to carry out technical, financial and administrative activities associated with the Loan application; and to approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #26-026 in the Water & Sewer Grant Fund to appropriate funding and recognize revenue in the amount of $5,342,266 for Phase I of the Hurricane Milton SRF Loan; and in the Water & Sewer Capital Improvement Fund to transfer $1,750,000 from Reserves for additional funding for WTP/WWTP Program Management. Countywide (Johnny Edwards, Utilities Director)
Attachments: 1. SRF LOAN RESOLUTION-GWL and Sewer - final.pdf, 2. Loan Application.pdf, 3. BAR 26-026.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

title

Approve and authorize the Chairman to execute a Resolution authorizing the County Manager to execute the Loan application and apply for a Loan through the Clean Water State Revolving Fund program, to provide assurances required by the Loan application, and delegate responsibility to appropriate Seminole County staff to carry out technical, financial and administrative activities associated with the Loan application; and to approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #26-026 in the Water & Sewer Grant Fund to appropriate funding and recognize revenue in the amount of $5,342,266 for Phase I of the Hurricane Milton SRF Loan; and in the Water & Sewer Capital Improvement Fund to transfer $1,750,000 from Reserves for additional funding for WTP/WWTP Program Management. Countywide (Johnny Edwards, Utilities Director)

end

Division:

division

Utilities - Water Utilities Engineering

body

Authorized By:

Johnny Edwards, Utilities Director

Contact/Phone Number:

Johnny Edwards/407-665-2005

Background:

On June 10, 2025, the Seminole County Board of County Commissioners (BCC) authorized the preparation and submittal of requests for funding of planned work related to the County‘s sanitary sewer system through the Florida Department of Environmental Protection’s (FDEP) Clean Water State Revolving Fund program with supplemental Federal appropriations for Hurricanes Helene and Milton. The County Manager submitted the request including projects at the Greenwood Lakes Water Reclamation Facility (GWLWRF) and the connected sanitary sewer transmission system.

On November 11, 2025, FDEP included Seminole County’s project on its award priority list and capped the recommended loan award at $19,166,503.00 with 50% loan forgiveness and 50% repaid at 0% interest over 20 years.

The loan application, due to FDEP by March 12, 2026, has been signed and submitted by the County Manager. The first item Resolution formalizes BCC ratification of the application for additional funds to assist the County in completing work that is necessary for the utility and included in the proposed Utilities Master Plan

The second item Resolution relates to a budget amendment request that includes $5,342,266 for preconstruction activities related to GWLWRF (part of the CWSRF projects) and $1,750,000 for program management to assist the County with planning and execution of the CWSRF and other Utilities projects. Construction funding will be budgeted following completion of preconstruction activities.

Water & Sewer Capital Improvement Fund Reserves are currently budgeted at $2.15 million.

Requested Action:

Staff requests to approve and authorize the Chairman to execute a Resolution authorizing the County Manager to execute the Loan application and apply for a Loan through the Clean Water State Revolving Fund program, to provide assurances required by the Loan application, and delegate responsibility to appropriate Seminole County staff to carry out technical, financial and administrative activities associated with the Loan application; and to approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #26-026 in the Water & Sewer Grant Fund to appropriate funding and recognize revenue in the amount of $5,342,266 for Phase I of the Hurricane Milton SRF Loan; and in the Water & Sewer Capital Improvement Fund to transfer $1,750,000 from Reserves for additional funding for WTP/WWTP Program Management.