SEMINOLE COUNTY, FLORIDA Header Image
File #: 2024-1046   
Category: Consent Item Status: Agenda Ready
File created: 7/18/2024 Type: Board of County Commissioners
On agenda: 8/27/2024 Final action:
Title: Approve and authorize the Chairman to execute a Memorandum of Agreement between The State of Florida Department of Transportation (FDOT) and Seminole County - FPID No. 417545-1-52-01 SR 417 (Seminole Expressway) Widening project from south of Aloma Avenue to north of SR 434. The project work contemplated by this agreement is to occur within the County's right-of-way at North Cross Seminole Trail, South Cross Seminole Trail, and Slavia Road. District1 - Dallari and District2 - Zembower (Jean Jreij, P.E., Public Works Director)
Attachments: 1. Memorandum of Agreement.pdf, 2. Exhibit A - Conceptual Plans (reduced).pdf, 3. Exhibit B - Maintenance Notes & Exhibits.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

title

Approve and authorize the Chairman to execute a Memorandum of Agreement between The State of Florida Department of Transportation (FDOT) and Seminole County - FPID No. 417545-1-52-01 SR 417 (Seminole Expressway) Widening project from south of Aloma Avenue to north of SR 434. The project work contemplated by this agreement is to occur within the County’s right-of-way at North Cross Seminole Trail, South Cross Seminole Trail, and Slavia Road. District1 - Dallari and District2 - Zembower (Jean Jreij, P.E., Public Works Director)

 

end

Division:

division

Public Works - Engineering

body

Authorized By:

Jean Jreij, P.E.

Contact/Phone Number:

Dennisse Zornan/407-665-5670

Background:

This Agreement contains all the necessary documents required for the successful execution of the MOA. The agreement outlines the scope of work, project improvements to be constructed within the County’s right-of-way as shown in Exhibit B, maintenance obligations, easement title, and air rights for all project facilities crossing County owned roadway, including, but not limited to, the bridges.

 

FDOT anticipates project construction to begin Spring 2024 and end Spring 2030. FDOT shall notify the County should any of these anticipated dates change. This agreement will remain in full force and effect for the duration of construction of the FDOT project.

 

Requested Action:

Staff requests the Board approve and authorize the Chairman to execute a Memorandum of Agreement between The State of Florida Department of Transportation and Seminole County related to the SR 417 (Seminole Expressway) Widening project (FPID 417545-1-52-01) from south of Aloma Avenue to north of SR 434.