Title: Approve Change Order #4 to CC-4845-23/HSM-Highland Pines-Graham Road Gravity Sewer Rehabilitation in the amount of $99,700.00 to Insituform Technologies, LLC of Chesterfield, Missouri, and an additional one hundred and fifty-one (151) calendar days to Substantial Completion and authorize the Purchasing and Contracts Division to execute the change Order. District4 - Lockhart (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Utilities
Attachments: 1. CC-4845-23 CO4 (Insituform).pdf

Title:

title

Approve Change Order #4 to CC-4845-23/HSM-Highland Pines-Graham Road Gravity Sewer Rehabilitation in the amount of $99,700.00 to Insituform Technologies, LLC of Chesterfield, Missouri, and an additional one hundred and fifty-one (151) calendar days to Substantial Completion and authorize the Purchasing and Contracts Division to execute the change Order. District4 - Lockhart (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Utilities

 

end

Division:

division

Resource Management - Purchasing and Contracts

body

Authorized By:

Lorie Bailey Brown, CFO/Resource Management Director

Contact/Phone Number:

Herronda S. Mortimer/407 665-7113

Background:

CC-4845-23/HSM provides sewer upgrades to the Highland Pines and

Graham Road service area. The project includes the furnishing and installation of sewer mains via pipe lining, individual sewer laterals to the

ROW, installation of clean-outs at the ROW and restorative efforts.

Change Order #4 will provide additional sewer lateral clean-outs added to the encompassed St. John’s apartments gravity sewer system (34 sewer lateral clean-outs), including three-ring and cover rehabilitation/replacement. The Change Order also adds one hundred fifty-one (151) calendar days to Substantial Completion.

 

The following is a summary of the cost of the Agreement:

 

Original Agreement Sum:                      $2,639,048.00

Change Order #1                                           $77,612.90

Change Order #2                                           $171,745.30

Change Order #3                                                               Time Only

Change Order #4                                                               $99,700.00

Revised Agreement Total                      $2,988,106.20

 

This is a budgeted project, and funds are available in Highland Pines Utilities

Upgrades (Acct #02108055.560650).

Requested Action:

Staff requests the Board approve Change Order #4 to CC-4845-23/HSM-Highland Pines-Graham Road Gravity Sewer Rehabilitation in the amount of $99,700.00 to Insituform Technologies, LLC of Chesterfield, Missouri., and an additional one hundred and fifty-one (151) calendar days to Substantial Completion and authorize the Purchasing and Contracts Division to execute the Change Order.