Title: Approve Amendment #7 to M-4970-23/RTB - Lockwood Boulevard Sewer Main Repair with Kiewit Water Facilities Co, Florida, of Miami, FL in the amount of $862,758.25 and authorize the Purchasing and Contracts Division to execute the Amendment. District1 - Dallari (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Utilities
Attachments: 1. M-4970-23 A7 (Kiewit).pdf, 2. Contractor Waiver and Release (Kiewit).pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

title

Approve Amendment #7 to M-4970-23/RTB - Lockwood Boulevard Sewer Main Repair with Kiewit Water Facilities Co, Florida, of Miami, FL in the amount of $862,758.25 and authorize the Purchasing and Contracts Division to execute the Amendment. District1 - Dallari (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Utilities

end

Division:

division

Resource Management - Purchasing and Contracts

body

Authorized By:

Lorie Bailey Brown, CFO/Resource Management Director

Contact/Phone Number:

Robert Bradley/407-665-7111

Background:

M-4790-23/RTB was undertaken as an emergency procurement to address the immediate repair of a collapsed sewer line on Lockwood Boulevard. The original emergency Agreement was issued to Kiewit Water Facilities Co, Florida and ratified by the Board during its February 28, 2023, meeting on the consent agenda.

As the project progressed, unexpected challenges emerged, necessitating additional work and funding. These include: (1) repairs to manholes and adjacent roadways not in the original scope of work which were necessary to ensure the safety, functionality, and structural integrity of the system; and (2) additional dewatering costs resulting from differing site conditions that created a need for extended dewatering activities to manage the groundwater levels, stabilize the site, and complete the repairs effectively.

Amendment 7 addresses the unanticipated costs and issues.

The following is a Cost Summary of the Agreement:

Original Contract Sum:                                           $1,518,000.00

Amendment 1:                                                                                    $     51,500.00

Amendment 2:                                                                                    Time Extension Only

Amendment 3:                                                                                    Time Extension Only

Amendment 4:                                                                                     Time Extension Only

Amendment 5:                                                                                     $                     6,923.33

Amendment 6:                                                                                     $                     1,224.50

Amendment 7:                                                                                    $    862,758.25

Revised Agreement Total                                           $ 2,440,406.08  

Funds are available in project 02308027 LOCKWOOD BLVD PIPE REPLACEMENT.

Requested Action:

Staff requests the Board approve Amendment #7 to M-7940-23/RTB in the amount of $862,758.25 and authorize the Purchasing and Contracts Division to execute the Agreement.