Title:
title
Approve and authorize Staff to proceed with the Maryland St/Astor Farms Outfall Project (CIP#02507061) in accordance with County Manager Policy #82 - Non-Board Approved Project; and approve and authorize the Chairman to execute a Resolution implementing Budget Amendment (BAR) #25-046 in the 2014 Infrastructure Sales Tax Fund to transfer $120,083 of existing budget to the Maryland St/Astor Farms Outfall Project from the Smith Canal Basin Project. District5 - Herr (John Slot, Public Works Director)
end
Division:
division
Management and Budget
body
Authorized By:
John Slot, Public Works Director
Contact/Phone Number:
Sara Carrick/407-665-7180
Background:
The Maryland St/Astor Farms Outfall Project (CIP#02507061) includes modification of existing outfall control structures on two ponds. In-house design was completed in March 2025. The lowest bid received for construction was with Schuller Contractors in the amount of $114,364. The department is requesting to add a 5% contingency which will increase the total amount needed to $120,083.
Funding for this project will come from the Smith Canal/Monroe Basin Project (CIP# 02007111). This project currently has $171K available and only needs $50K in funding for ongoing basin studies. There will be no impact to 2014 Infrastructure Sales Tax Fund reserves.
Requested Action:
Staff requests the Board dpprove and authorize Staff to proceed with the Maryland St/Astor Farms Outfall Project (CIP#02507061) in accordance with County Manager Policy #82 - Non-Board Approved Project; and approve and authorize the Chairman to execute a Resolution implementing Budget Amendment (BAR) #25-046 in the 2014 Infrastructure Sales Tax Fund to transfer $120,083 of existing budget to the Maryland St/Astor Farms Outfall Project from the Smith Canal Basin Project.