Title:
title
Approve Change Order #10 to CC-3793-21/RTB - EE Williamson Road Trail Connection & Intersection Improvements at Rangeline Road in the amount of $150,321.91, to Hubbard Construction Company of Winter Park, Fl., and authorize the Purchasing and Contracts Division to execute the Change Order. District4 - Lockhart (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Public Works
end
Division:
division
Resource Management - Purchasing and Contracts
body
Authorized By:
Lorie Bailey Brown, CFO/Resource Management Director
Contact/Phone Number:
Robert T. Bradley/407-665-7111
Background:
CC-3793-21/RTB is providing all labor, materials, transportation, coordination, and incidentals necessary for the construction of a trail along EE Williamson Rd and sidewalk along Longwood Hills Road, and a pedestrian bridge just west of Ronald Reagan Blvd.
Change Order #10 will provide the final pay item and time adjustments to the project to reach final completion.
The following is a summary of the cost of the Agreement:
Original Agreement Sum: $7,975,430.26
Change Order #1 (253,526.42)
Change Order #2 17,521.58
Change Order #3 16,642.50
Change Order #4 16,443.26
Change Order #5 167,832.74
Change Order #6 166,628.56
Change Order #7 3,282.27
Change Order #8 141,700.37
Change Order #9 204,251.16
Change Order #10 150,321.91
Revised Agreement Total $8,606,528.19
This is a budgeted project and funds are available in Infrastructure Sales Tax (Account# 01785316.560650.00001.
Requested Action:
Staff requests that the Board approve Change Order #10 to CC-3793-21/RTB - EE Williamson Road Trail Connection & Intersection Improvements at Rangeline Road with Hubbard Construction Company of Winter Park, Fl., in the amount of $150,321.91; and authorize the Purchasing and Contracts Division to execute the Change Order.