Title: Approve Change Order #10 to CC-3793-21/RTB - EE Williamson Road Trail Connection & Intersection Improvements at Rangeline Road in the amount of $150,321.91, to Hubbard Construction Company of Winter Park, Fl., and authorize the Purchasing and Contracts Division to execute the Change Order. District4 - Lockhart (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Public Works
Attachments: 1. CC-3793-21 CO10 (Hubbard).pdf

Title:

title

Approve Change Order #10 to CC-3793-21/RTB - EE Williamson Road Trail Connection & Intersection Improvements at Rangeline Road in the amount of $150,321.91, to Hubbard Construction Company of Winter Park, Fl., and authorize the Purchasing and Contracts Division to execute the Change Order. District4 - Lockhart (Lorie Bailey Brown, CFO/Resource Management Director) Requesting Department - Public Works

end

Division:

division

Resource Management - Purchasing and Contracts

body

Authorized By:

Lorie Bailey Brown, CFO/Resource Management Director

Contact/Phone Number:

Robert T. Bradley/407-665-7111

Background:

CC-3793-21/RTB is providing all labor, materials, transportation, coordination, and incidentals necessary for the construction of a trail along EE Williamson Rd and sidewalk along Longwood Hills Road, and a pedestrian bridge just west of Ronald Reagan Blvd.

 

Change Order #10 will provide the final pay item and time adjustments to the project to reach final completion.

 

The following is a summary of the cost of the Agreement:

Original Agreement Sum:                                           $7,975,430.26

Change Order #1                                                                    (253,526.42)

Change Order #2                                                                       17,521.58

Change Order #3                                 16,642.50

Change Order #4                                 16,443.26

Change Order #5                               167,832.74

Change Order #6                               166,628.56

Change Order #7                                                                         3,282.27

Change Order #8                                                                     141,700.37

Change Order #9                                                                     204,251.16

Change Order #10                                                                   150,321.91

Revised Agreement Total                                $8,606,528.19

 

This is a budgeted project and funds are available in Infrastructure Sales Tax (Account# 01785316.560650.00001.

 

Requested Action:

Staff requests that the Board approve Change Order #10 to CC-3793-21/RTB - EE Williamson Road Trail Connection & Intersection Improvements at Rangeline Road with Hubbard Construction Company of Winter Park, Fl., in the amount of $150,321.91; and authorize the Purchasing and Contracts Division to execute the Change Order.