Skip to main content
SEMINOLE COUNTY, FLORIDA Header Image
File #: 2025-471   
Category: Consent Item Status: Agenda Ready
File created: 5/5/2025 Type: Board of County Commissioners
On agenda: 7/22/2025 Final action:
Title: Approve Change Order #2 to CC-5761-24/MAG - Construction Services Agreement for the Lake Mary Blvd at Country Club Road Intersection Improvements Project in the amount of $261,531.52 with Central Florida Environmental (CFE) Corporation and authorize the Purchasing and Contracts Division to execute this Change Order; and approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #25-061 in the Core Mobility Fund to appropriate funding in the amount of $376,631. District4 - Lockhart (Stephen Koontz, Resource Management Deputy Director) Requesting Department - Public Works
Attachments: 1. CC-5761-24 CO#2 Approval Memo.pdf, 2. CC-5761-24 CO#2 (CFE).pdf, 3. BAR 25-061 - LAKE MARY BLVD & COUNTRY CLUB.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

title

Approve Change Order #2 to CC-5761-24/MAG - Construction Services Agreement for the Lake Mary Blvd at Country Club Road Intersection Improvements Project in the amount of $261,531.52 with Central Florida Environmental (CFE) Corporation and authorize the Purchasing and Contracts Division to execute this Change Order; and approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #25-061 in the Core Mobility Fund to appropriate funding in the amount of $376,631. District4 - Lockhart (Stephen Koontz, Resource Management Deputy Director) Requesting Department - Public Works

end

Division:

division

Resource Management - Purchasing and Contracts

body

Authorized By:

Robert Bradley, Purchasing Manager

Contact/Phone Number:

Michael Guild/407-665-7122

Background:

CC-5761-24/MAG provides construction services for the widening the existing southbound lane along Country Club (from Lake Mary Blvd to 3rd St.); widening the existing northbound right turn lane along Country Club (from the existing driveway to Lake Mary Blvd); widening the existing northbound right turn lane along Country Club (from Lake Mary Blvd to E. Lakeview Ave); extension of existing eastbound left turn lane along Lake Mary Blvd; and the construction of four (4) new mast arms at the intersection.

Change Order #2 will provide for additional funding (9%) to cover cost increases associated with unforeseen site conditions and associated additional work. The change order exceeds 5% of the original contract, requiring Board approval. Following is a Cost Summary of this Agreement:

Original Contract Sum: $2,915,290.75

Change Order #1: (Time Only - No Change in Dollar Amount)

Change Order #2: (+ $261,531.52)

Revised Agreement Total: $3,176,822.27

Budget Amendment Request (BAR) #25-061 is a request to add additional funds for Change Order #2 and the Construction Engineering and Inspection (CEI) Workorder 12  in order to extend and continue services due to the addition of 91 days to the construction contract. Additional funds are also needed for Post Design Services to reflect final constructed conditions including changes made during construction.

The cost is consistent for a construction project.

Requested Action:

Staff requests the Board approve Change Order #2 to CC-5761-24/MAG - Constructions Services Agreement for the Lake Mary Blvd at Country Club Road Intersection Improvements Project, in the amount of $261,531.52 with CFE Corporation, and authorize the Purchasing and Contracts Division to execute the Change Order; and approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #25-061 in the Core Mobility Fund to appropriate funding in the amount of $376,631.