Title: Approve Change Order #7 to CC-4727-23/GCM - Sand Lake Road at SR 434 & Sand Lake Rd at W. Lake Brantley Road Intersection Improvements with Southland Construction in the amount of $6,955.99 and authorize the Purchasing and Contracts Division to execute the Change Order. District3 - Constantine. (Stephen Koontz, Administrative Services Deputy Director) Requesting Department - Public Works
Attachments: 1. CC-4727-23 CO7 (Southland).pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title:

title

Approve Change Order #7 to CC-4727-23/GCM - Sand Lake Road at SR 434 & Sand Lake Rd at W. Lake Brantley Road Intersection Improvements with Southland Construction in the amount of $6,955.99 and authorize the Purchasing and Contracts Division to execute the Change Order. District3 - Constantine. (Stephen Koontz, Administrative Services Deputy Director) Requesting Department - Public Works

end

Division:

division

Administrative Services - Purchasing and Contracts

body

Authorized By:

Robert Bradley, Purchasing Manager

Contact/Phone Number:

Robert Bradley/407-665-7111

Background:

CC-4727-23/GCM will provide construction of turn lanes, sidewalks, and a Mast Arm/Pedestrian Signal, adjustment of drainage structures and modification of driveways at 2 locations on Sand Lake Road at SR434 and Sand Lake Road at West Lake Brantley Road.

Change Order #5, which increased the contract value by 7% over the original contract amount and in accordance with the Construction Change Orders policy exceeding the 5% threshold was approved by the Board on July 22, 2025.   Change Order #7, at $6,955.99, follows cumulative changes that exceed the 5% threshold, and requires Board approval under the same policy for execution.

Change Order #7 is for final quantity adjustments (overruns and underruns) prior to closeout.  The contract time is also extended by five (5) days per the Change Order documents.

The following is a summary of the cost of the Agreement:

Original Agreement Sum:                                          $2,781,977.24

Change Order #1                                                               TIME ONLY

Change Order #2                                                               $    13,978.11

Change Order #3                                                               $  125,821.37

Change Order #4                                                               TIME ONLY

Change Order #5                                                               $   54,631.70

Change Order #6                                                               $     6,070.17

Change Order #7                                                               $      6,955.99

Revised Agreement Total                                          $2,989,434.58

This is a budgeted project, and funds are available in SR434/SAND LK RD INT IMP (Acct# 01785147.560650.00001)

Requested Action:

Staff requests that the Board approve Change Order #7 to - Sand Lake Road at SR 434 & Sand Lake Rd at W. Lake Brantley Road Intersection Improvements with Southland Construction in the amount of $6,955.99, and authorize the Purchasing and Contracts Division to execute the Change Order.