File #: 2023-185   
Category: Consent Item Status: Passed
File created: 2/9/2023 Type: Board of County Commissioners
On agenda: 2/28/2023 Final action: 2/28/2023
Title: Approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #23-031 in the 2014 Infrastructure Sales Tax Fund to transfer $330,054 from reserves for additional funding of the Little Wekiva River Restoration Project. Countywide (Timothy Jecks, Deputy CFO / Budget Division Manager) - Requesting Department: Public Works
Attachments: 1. BACK UP - BAR 23-031.pdf

Title:

title

Approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #23-031 in the 2014 Infrastructure Sales Tax Fund to transfer $330,054 from reserves for additional funding of the Little Wekiva River Restoration Project. Countywide (Timothy Jecks, Deputy CFO / Budget Division Manager) - Requesting Department: Public Works

end

Division:

division

Resource Management - Budget

body

Authorized By:

Lorie Bailey-Brown, CFO/Resource Management Director

Contact/Phone Number:

Sara Carrick, Financial Administrator - 407-665-7180

Background:

The Little Wekiva River Restoration Project (LWRRP) involves restoration efforts for approximately 20 acres of land around the Little Wekiva River from north of Springs Landing Bridge to just south of SR46. These restoration efforts include sediment and vegetation removal, revegetation, and aquatic plant management and are being managed by Seminole County. Government agencies including St. Johns River Water Management District (SJRWMD), Florida Department of Environmental Protection, and Federal Environmental Protection Agency are all providing grant funding totaling $2.043M for these activities and County match of approximately $2.5M coming from 2014 Infrastructure Sales Tax funds.

The remaining cost estimates for this project include $3,842,032 for vegetation/sediment removal; $100,000 for revegetation; $25,000 for aquatic plant management activities and a 5% contingency at $198,353. In total, the project is estimated to need $4,165,385 in the current fiscal year budget to complete. Currently, the budget has $3,835,331 in available funds. The attached BAR will add $330,054 from Infrastructure Sales Tax Fund reserves to complete the project. Reserves in the 2014 Infrastructure Sales Tax fund are currently budgeted at $9.5M

 

recommendation

Staff Recommendation:

Staff recommends that the Board approve and authorize the Chairman to execute a Resolution implementing Budget Amendment Request (BAR) #23-031 in the 2014 Infrastructure Sales Tax Fund to transfer $330,054 from reserves for additional funding of the Little Wekiva River Restoration Project.